SYSTEM REFERENCE / Manufacturing

CNC tending: robot–machine handshake planning

Load blanks and unload parts with explicit acknowledgments and fault exits.

Reference · unverified
Version
v0.1.0
Source review
2026-11-07
Publication
Task & system reference
SYSTEM OVERVIEWDiagram · not a running system
  1. 01Machine ready
  2. 02Door/clamp confirmation
  3. 03Load/unload
  4. 04Exit and request cycle
Interfaces and conditions are documented below

Implementation & checks

Follow this version’s assumptions and steps. Unperformed steps are not passed tests.

  1. 01

    List states

    Record requests, acknowledgments, timeouts and reset responsibility; fixed delays do not prove completion.

  2. 02

    Validate separately

    Validate interfaces and fault exits under controlled conditions before real parts.

  3. 03

    Define acceptance

    Check misclamps, dropped parts, door failures and recovery; record interventions.